Construction is set to conclude this summer on two RRISD high schools, which will open Aug. 26 for the 2014–15 school year.
Round Rock High School Master Plan Phase 3 construction includes shifting the main entrance of the school from Lake Creek Drive to Deepwood Drive. The 139,569-square-foot expansion includes 40 classrooms, a culinary classroom and a mock courtroom for the school's criminal justice program.
The rebuilt campus includes a new administrative office and a school store. Tim Strucely, director of facilities and construction, said the store will be used by RRHS' business academy.
To date, the cost for Phase 3 is $25,481,354, said Corey Ryan, RRISD associate director of community relations. Architecture firm PBK designed Phase 3 for the school.