Pflugerville officials expect the current phase of construction on Kelly Lane to be completed on schedule in December despite engineering hitches and unexpected delays.
The portion of Kelly Lane between Falcon Pointe Boulevard West and Murchison Ridge Trail is currently slimmed to a narrow, two-lane road bordered by orange barrels and barricades.
The goal of the project is to widen the road and add turn lanes, sidewalks, medians and new traffic signals. The changes are designed to relieve traffic around area homes, schools, businesses and the soon-to-be-open Hawaiian Falls Water and Adventure Park at SH 130 and FM 685. Raised curbs and stormwater drains will also be installed.
Roadwork on Kelly Lane began in December 2013. Work crews ran into underground infrastructure that builders and city officials did not know existed. Some of the pipes and cables that crews have uncovered are so old they do not appear on any plans, Pflugerville City Engineer Dan Franz said. Builders hit what Franz referred to as a "live" wastewater main that was not noted in plans.