New construction needs will push the completion of the Richardson Public Library renovation to May or June and its opening to September, according to a presentation at the Feb. 2 City Council meeting.
Council approved an additional $1.18 million to address water infiltration issues that arose during construction.
What’s happening?
The library renovation project began in spring 2024, and work is about 75% complete, Assistant City Manager Charles Goff said. In August, council approved an additional $1.15 million to the $48.1 million budget to address some construction challenges.