As part of a separate project, the city plans to convert all downtown streets to concrete in the next 10-15 years.
Downtown streets slated for full-depth reclamation during this year’s annual maintenance are roadways that will not be converted to concrete in the near future, Figueroa said.
What else?
The 2026 Annual Street Maintenance program also involves various smaller repairs around Celina, such as:
- Surface treatments
- Crack sealing
- Roadway striping
- Asphalt spot repairs
- Concrete panel replacement
- Sidewalk replacements
To reduce the impact on residents, Celina uses a method for surface treatments called pressure paving where construction crews spray roadways with a thin asphalt overlay, Figueroa said.