1. Preston Road improvements
The projects to add double left-turn lanes on the northbound and southbound sides of Preston Road at (A) Hedgcoxe Road, Headquarters Drive, Tennyson Parkway, Spring Creek Parkway, and (B) Parker Road, are open to the public. The contractor is working on sidewalks and other miscellaneous items to complete the job.
Timeline: September 2013-July 2016 Cost: $4.6 million Funding sources: city of Plano, North Central Texas Council of Governments
2. Independence Parkway repairs
The project to repair the roadway along Independence Parkway is on schedule. Lane closures will continue to take place from (A) Plano Parkway to West 15th Street and from (B) Cross Bend Road to West Spring Creek Parkway. The crews will meet in the middle between 15th Street and West Parker Road, where an ultrathin layer of a new, more flexible type of asphalt will be applied.
Timeline: January 2016-January 2017 Cost: $4.2 million Funding sources: city of Plano, Collin County