Clay Lipscomb, the city’s community investment program engineering manager, said water rehabilitation projects last between nine to 12 months depending on its size, and work is done in phases:
- First: The city installs and switches services to the new PVC pipes. Any removed pavement might be replaced with temporary asphalt. This phase might take two to three weeks for each street.
- Second: The contractor removes temporary asphalt and installs permanent concrete for streets that have had their water mains replaced. This phase might take a week or two for each street.
- Third: The contractor fixes any additional project items, like replacing disturbed sod, which Lipscomb said can take a couple of weeks of work.
Lipscomb said residents living in a project area can expect to see workers for one to two months on their street. He added the timeline could change depending on the street and neighborhood.
The specifics
The city has at least eight recently completed, ongoing or upcoming projects related to distribution main replacements for PVC pipes. Impacted neighborhoods include:
- Old Shepard Place in west Plano
- Kimberlea Additions, Kimberlea Estates, Parkway Estates, Whiffletree Addition, Prairie Creek, Post Oak and River Bend in central Plano
- Douglas Community, Creekside Estates, Los Rios Estates and Ranch Estates in east Plano
Park Boulevard also saw distribution main replacements, with its first phase completed in April 2026 and its second phase completed in September 2025, per
previous reporting.
The city’s project in the Douglass Community started in May, according to the city’s community investment project dashboard. Communities like the Parkway Estates and Whiffletree Addition are estimated to start in August, while the Kimberlea Additions will start in November.