Parker Road repairs An 18-month construction project on Parker Road began in June. Crews will be working on both eastbound and westbound lanes spanning from Rainier Road to Alma Drive. The nearly $4 million project is expected to last into late 2020. One lane will remain closed at all times in construction areas, with an additional lane closed from 9 a.m.-4 p.m. on weekdays and some Saturdays. Timeline: June 2019-late 2020 Cost: $3.8 million Funding source: city of Plano
City & CountyPlano
Project on Parker Road in Plano to continue into late 2020
Project on Parker Road in Plano to continue into late 2020