Work along FM 518 in Pearland is coming, but officials said it’ll be likely a couple more years before construction begins.
Explained
Construction along FM 518, which will be broken up into work on both the east and west sides of the road in Pearland, are in the design phases, said Danny Perez, public information officer for the Texas Department of Transportation.
As of May, the design phase for the project for the east side of FM 518, which will cover a 3-mile stretch from east of Freedom Road to the east of Halbert Road, is 60% complete and is likely to be bid out toward the beginning of 2027, Perez said.