Curious as to what new businesses and renovations are underway or coming to Pearland and Friendswood? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Yonutz: 11200 Broadway St., Pearland
Type of work: renovation/alteration
Timeline: Oct. 17, 2022-Jan. 6, 2023
Estimated cost: $157,858
2. Safelite Autoglass: 2633 Miller Ranch Road, Pearland
Type of work: renovation/alteration
Timeline: Nov. 14, 2022-Jan. 16, 2023
Estimated cost: $354,000
3. Space City Heat: 3525 Main St., Ste. 154, Pearland
Type of work: renovation/alteration
Timeline: Sept. 30, 2022-Aug. 29, 2023
Estimated cost: $50,000
4. Spout Car Wash: 9540 Broadway St., Pearland
Type of work: new construction
Timeline: Jan. 9, 2023-July 28, 2023
Estimated cost: $1.2 million
5. Shadow Creek: 12322 Shadow Creek Parkway, Pearland
Type of work: renovation/alteration
Timeline: Sept. 19, 2022-Jan. 9, 2023
Estimated cost: $750,000
6. Buc-ee’s: 11200 Broadway St., Ste. 2338, Pearland
Type of work: renovation/alteration
Timeline: Sept. 1-Dec. 1
Estimated cost: $375,000
*7. Windsong Elementary School: 2100 W. Parkwood Ave., Friendswood
Type of work: additions to existing building
Timeline: Oct. 17, 2022-July 24, 2023
Estimated cost: $6 million
8. Bales Intermediate School: 211 Stadium Lane, Friendswood
Type of work: renovation/alteration
Timeline: May 29, 2023-July 24, 2023
Estimated cost: $1 million
9. Kids Foot Locker: 500 Baybrook Mall, Ste. 1130, Friendswood
Type of work: renovation/alteration
Timeline: Jan. 9, 2023-Jan. 27, 2023
Estimated cost: $100,000
10. Dr. Martens: 500 Baybrook Mall Drive, Friendswood
Type of work: renovation/alteration
Timeline: July 1-Sept. 25
Estimated cost: $576,778
*Note: The school exists as Windsong Intermediate but will switch over to Windsong Elementary School for the 2023-24 school year, according to Friendswood ISD officials.