The South Castell Visioning Plan identified the center as a key redevelopment opportunity, calling for adjacent uses like hotels, residential units and improved public spaces. The feasibility study with C.H. Johnson Consulting will directly advance those goals by using up-to-date market and financial analysis to determine what is viable, agenda documents state.
The project will consist of the following four phases:
- Phase 1: market viability analysis
- Phase 2: demand and financial feasibility
- Phase 3: conceptual site planning
- Phase 4: economic impact and implementation study
The market viability analysis will examine the city's market relative to regional and national trends. The second phase will provide usage level projections for an expanded facility.
"That second phase will be where the data and analysis can then start to determine how the facility should be expanded to support the existing and, more importantly, new demand," Assistant City Manager Jared Werner said.
Then the firm will use those findings to draw out site concepts. The fourth and final phase of the process will include estimates for direct and indirect economic benefits for new jobs and sales taxes. This phase will also look at potential funding strategies and outline a roadmap for implementation, Werner said.