The New Braunfels ISD board of trustees approved a $101,232 change order and time extension on Aug. 11 for Joeris Construction to complete the first phase of reconstructing New Braunfels High School.
What you need to know
The contractual date for substantial completion of Phase 1 was late September, but because of a design change related to the construction of the main entrance and the decision to keep four existing tennis courts, the completion date has moved to late October, according to board documents.
The decision to keep the existing tennis courts created design issues in the sub surface preparation for the new curbs and drive on the east side of the Phase 1 building. Each of the aforementioned issues were discovered as construction progressed and required additional discovery and planning, board documents state.