Comal ISD board members received an update on a number of 2021 and 2023 bond projects across the district at a board meeting Feb. 26.
The details
Three projects are funded by the voter-approved 2021 bond, which allocated $411.3 million for the construction of two new elementary schools, one new middle school, land acquisition and infrastructure projects, according to the district’s website.
The remaining projects are funded by the voter-approved 2023 bond, which allocated $560.6 million to the construction of three new elementary schools, an additional middle school, the Life Bridges replacement campus and safety and security projects across the district, according to the district's website.
Completed
Smithson Valley High School
- Project: heating, ventilation and air conditioning controls upgrade
- Update: work to replace HVAC controllers on campus continues
- Timeline: October 2025-March 2027
- Funding: 2021 bond
- Cost: $53,800
Canyon High School
- Project: exhaust fan replacement
- Update: completed
- Timeline: November 2025-February 2026
- Funding: 2021 bond
- Cost: $523,000
Canyon Lake High School
- Project: construction of baseball and softball facilities
- Update: completed
- Timeline: July 2025-February 2026
- Funding: 2023 bond
- Cost: $11.02 million
Memorial Early College High School
- Project: HVAC and roof replacement
- Update: project is complete
- Timeline: October 2025-February 2026
- Funding: 2023 bond
- Cost: $4.58 million
Ongoing
Canyon High School
- Project: 70,000 square feet of walkway floor renovations
- Update: lighting upgrades and remaining interior finishes scheduled to begin in the summer
- Timeline: November 2025-August 2026
- Funding: 2021 bond
- Cost: $703,000
Middle School No. 9
- Project: construction of new middle school
- Update: second-floor concrete placement complete, exterior work underway
- Timeline: February 2025-April 2027
- Funding: 2023 bond
- Cost: $123.55 million
Life Bridges (Main Campus)
- Project: construction of a new campus to educate young adults with disabilities, ages 18-21, to aid transition into the community
- Update: foundation preparation and concrete placement in progress
- Timeline: February 2025-Fall 2026
- Funding: 2023 bond
- Cost: $15.98 million
Elementary School No. 22
- Project: construction of new elementary school
- Update: contractor preparing the site
- Timeline: February 2026-Summer 2027
- Funding: 2023 bond
- Cost: $71.89 million
Smithson Valley High School
- Project: construction of new Junior Reserve Officers' Training Corps and Wrestling building
- Update: masonry work and framework progressing
- Timeline: July 2025-August 2026
- Funding: 2023 bond
- Cost: $5 million
Smithson Valley High School
- Project: construction of dance, cheer and athletic locker rooms
- Update: construction plans finalized
- Timeline: April 2025-August 2026
- Funding: 2023 bond
- Cost: $5 million
Canyon Middle School
- Project: roof repair and replacement for middle school
- Update: construction began in March
- Timeline: March 2026-August 2026
- Funding: 2023 bond
- Cost: $736,000
Church Hill Middle School
- Project: HVAC repair and replacement
- Update: crews expected to move furniture at end of the school year to continue HVAC replacement work
- Timeline: October 2025-August 2026
- Funding: 2023 bond
- Cost: $3.04 million
Canyon High School
- Project: construction of tennis and golf facilities
- Update: excavation in progress
- Timeline: December 2025-August 2026
- Funding: 2023 bond
- Cost: $181,000
Canyon High School