New Braunfels City Council approved an agreement with engineering firm Freese and Nichols, Inc. for the final plans, specifications and estimated cost for the construction of the east portion of Alligator Creek Trail Dec. 8.
Alligator Creek is a 6.5 mile trail being built in two different segments: east and west, New Braunfels Park Development Manager Jeff Bransford told Community Impact. The east segment of the trail will be approximately 4 miles and "meander" through the Creekside shopping area, down to FM 1101 and connect with some of the nearby residential areas to create a loop that goes back toward Sophie Lane, Bransford said.
The details
The firm submitted a proposal for final design and construction administration services not to exceed $780,438. The scope includes final trail alignment, floodplain hydrologic and hydraulic analysis, environmental permitting, subsurface utility engineering, utility coordination and outreach, according to agenda documents.