1. Lake Forest Drive
On June 21, McKinney City Council voted to award a contract to Mario Sinacola and Sons Excavating Inc. for the construction of the Lake Forest Drive extension from Wilmeth Road to Bloomdale Road.
The city will also be making improvements to the intersection at CR 164. CR 164 is a one-lane, narrow roadway that will be expanded to two lanes and will allow better access to Erwin Park.
City officials said the project is expected to begin at the end of July or the beginning of August. Construction should end by May 2017.
Timeline: July-May 2017 Cost: $3,743,175.45 Funding sources: city of McKinney