Curious about the latest developments in McKinney? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.
Dave’s Hot Chicken: 4040 W. University Drive, Ste. 100, McKinney
Type of work: renovation/alteration
Timeline: March 1-June 1
Estimated cost: $250,000
Aura McKinney: southeast corner of Stacy Road and Kickapoo Drive, McKinney
Type of work: new construction
Timeline: May 1, 2022-May 1, 2024
Estimated cost: $44 million
Capriotti’s Sandwich Shop: 3194 W. University Drive, Ste. 600, McKinney
Type of work: new construction
Timeline: April 15-July 15
Estimated cost: $325,000
Salad and Go: 4751 S. Custer Road, McKinney
Type of work: new construction
Timeline: June 3-Sept. 5
Estimated cost: $300,000
Strickland Brothers Oil: McKinney Ranch Parkway, McKinney
Type of work: new construction
Timeline: April 1-Oct. 31