Here are five ongoing transportation projects in western Travis County, according to county information.
Ongoing projects
Bee Creek Sports Complex, Phase II
Work includes the construction of synthetic sports Fields 6 and 7 and associated infrastructure at Bee Creek Sports Complex.
- Update: Construction is 20% complete as of April.
- Timeline: end of 2025-third quarter of 2026
- Cost: $6.95 million
- Funding source: Travis County 2023 bond
Hamilton Pool Road Safety Improvement Project Phase IIThe project will add shoulders, turn lanes and an increasing curve radius along Hamilton Pool Road, from east of the Pedernales River to east of High Plains Drive.
- Update: Design for the project is complete, and the project in full is 50% complete as of April.
- Timeline: second quarter of 2026-end of 2026
- Cost: $2.39 million
- Funding source: Travis County bonds
Upcoming projectsDeer Creek Substandard Road Project II
The project will update parts of Deer Creek Skyview, Janey Loop, Little Creek Circle, Hilltop Drive and Village Drive to meet the Travis County standards required to integrate the roads into ongoing county maintenance programs.
- Update: The project is 40% designed as of April.
- Timeline: design completed in second quarter of 2026, construction TBD
- Cost: TBD
- Funding source: Travis County
Deer Creek Substandard Road Project IThe project will update parts of Glenview Circle, Lake Park Drive, Creekwood Circle, Ridgeview Circle, Westlake Drive and Parkwood Drive to meet the Travis County standards required to integrate the roads into ongoing county maintenance programs.
- Update: Design is 10% complete as of April.
- Timeline: design completed second quarter of 2026, construction TBD
- Cost: TBD
- Funding source: Travis County
Cardinal Hills Estates street improvements The project will improve right of way for sections of Lawrence Drive, Sutton Drive and Lariat Trail to meet the Travis County standards required to integrate the roads into ongoing county maintenance programs.
- Update: The project is 7% complete as of April.
- Timeline: design to be completed fourth quarter of 2026
- Cost: TBD
- Funding source: Travis County