After more than four years of construction, work on a $128.2 million project to widen FM 1960 in the Lake Houston area is expected to wrap up in April, officials with the Texas Department of Transportation confirmed March 18.
The overview
In late 2021, road work began on a two-part project that widened FM 1960 from a four-lane asphalt roadway to a six-lane divided concrete roadway. TxDOT Public Information Officer Bambi Hall said the project consists of a raised median, curbs and gutters, channelized left-turn lanes and 5-foot sidewalks on both sides of the roadway.
Segment A—a $58.2 million project—runs from Business FM 1960 to east of Twigsworth Lane, while Segment B—a $70 million project—continues to the western approach of the McKay Bridge at Lake Houston.