Harris County Precinct 2 completed the widening of Timber Forest Drive from a two- to four-lane road between Eagle Springs and Madera Run parkways in early September. The mobility project was originally scheduled to be completed in early July, but weather delays pushed the completion date, according to Harris County Precinct 2 officials. Timeline: November 2018-Sept. 9 Cost: $3 million Funding source: Harris County Precinct 2