Stay informed on four road projects happening in Keller, Roanoke and northeast Fort Worth. This list is not comprehensive
Upcoming projects
1. North Oak Street updates
Project: Roadwork on North Oak Street will be from Byron Nelson Boulevard to Dorman Street and include a 31-foot curbed roadway, installation of new storm drain infrastructure and cross culverts to replace the existing open ditches, replacement of water and sewer lines and the addition and replacement of sidewalks.
Update: The project is in the design phase and will take at least six months to complete since design work began in April.
- Timeline: designs to finish in six to eigth months
- Cost: $411,530
- Funding sources: city of Roanoke, Denton County
Ongoing projects
2. FM 1938 median project
Project: The work will include converting the two-way left-turn lane into a 14-foot-wide raised median. At intersections with median breaks, the median will be reduced to a width of 2 feet, and a 12-foot-wide left-turn lane will be created. The project will be from Southlake Boulevard to Emerald Hills Way, and lane configuration will not change. Additionally, the road from FM 1709 to Starnes Road will be reconstructed.
Update: Workers moved into Keller, and drivers will encounter moving interior-lane closures as progress continues south toward North Richland Hills. Work in Keller is expected to finish in June.
- Timeline: March-summer 2027
- Cost: $9.9 million
- Funding source: Texas Department of Transportation
3. North Beach Street and Champions View Parkway traffic signal
Project: The work includes the installation of a new traffic signal with a new pedestrian sidewalk and crosswalks, Americans with Disabilities Act-compliant ramps and Accessible Pedestrian Signals.
Update: The contractor is now installing signs, pavement striping and landscaping. The project team is coordinating with Tri-County Electric to schedule crews on-site to provide power to the traffic light.
- Timeline: traffic light activation expected to occur at the end of May
- Cost: $2 million
- Funding source: city of Fort Worth
4. Ray White Road widening improvements
Project: Ray White Road will be widened to a four-lane divided road between Mirage Drive and the bridge over Bear Creek. Additional improvements include adding a sidewalk on both sides of the road, installing street lights, storm drain improvements and constructing modifications to the roundabout at Ray White Road and Park Vista Boulevard
Update: The main lanes and roundabout modifications are now paved. The contractor is in the process of pouring sidewalks and finalizing the installation of streetlights and the traffic signal at Wall Price.
- Timeline: expected to finish late summer, early fall
- Cost: $22 million
- Funding source: city of Fort Worth