Construction on a new parking garage in downtown Roanoke is scheduled to start Feb. 23 and bring 430 parking spots to Oak Street, according to a news release from the city of Roanoke.
What you need to know
The parking garage will be located on 0.902 acres at 102 S. US 377. The current parking lot will close Feb. 21 to allow for fencing and erosion control installation, per the release.
Construction is anticipated to finish in March 2027, Public Engagement Manager Sandra Pettigrew said.
During construction, nearby properties can expect:
- Increased construction-related noise and lighting
- Heavy equipment and truck activity
- Temporary lane closures or traffic adjustments along US 377 and nearby streets
- Changes to parking access in the immediate area
A construction trailer will be placed at the lot located at 101 Main St., which is behind
Neill Insurance Brokers and
Mugs Café & Bakery.
Additionally, equipment and supplies will be staged at the lot just north of American National Bank & Trust, which is located at 409 S. Oak St.
More details
The parking garage will be five stories tall and cost the city $22 million, which will be paid for using a certificate of obligations bond, Community Impact previously reported.
The new parking structure will help the city address a parking issue based on a traffic study that was completed for Oak Street in 2019.