Fulshear residents will be able to enjoy improvements to Primrose Park as early as 2027.
What’s going on
At a Nov. 17 meeting, Fulshear City Council approved a $7.6 million construction contract with Crain Group LLC for the third phase of Primrose Park, located at 7622 Dixon Road.
Matthew Riley, project manager with the public works department, said the scope of work includes:
Crain Group will also be responsible for enlarging the existing detention pond and changing it into an amenitized wet-bottom pond with a neighboring sidewalk, Riley said.
Budget explained
The Primrose Park improvements are funded by the May 2025 voter-approved parks bond with a total budget of $10.5 million.
Assistant Public Works Director David Licon said the roughly $3 million difference between what was budgeted and the contract amount will go toward additional improvements such as expanding the amphitheater, installing audio and visual equipment, building another restroom and purchasing an aerator.
“Now we can do some of the more fun things that I think the city would like to see in a park that we’ve invested so much in,” Licon said.
Remember this?
Fulshear officials gathered June 13 to throw the ceremonial first pitch signifying the opening of the second phase of construction at Primrose Park, which includes four baseball and softball fields.
Other Phase 2 features include:
Sports lighting for all fields
A restroom and concession building
Parking and required detention
Officials previously said Phase 1 of the project included walking trails and parking.
Stay tuned
Construction is set to begin in December and is expected to last nine months, Riley said.