1.) Gosling Road at West Rayford traffic signal

Project: Modify existing signal with a new mast arm traffic signal in order to improve traffic flow and safety along Gosling Road. The Harris County Precinct 3 Commissioner’s Office is overseeing the design work.

Update: Design work is underway for a potential light at the intersection.
  • Cost: TBD
  • Timeline: Early 2027
  • Funding source: Harris County, TxDOT


2.) Spring Cypress Road asphalt rehabilitation


Project: Asphalt rehabilitation for Spring Cypress Road, from west of Stuebner Airline to east of TC Jester Blvd. and Louetta Road, then from Old Louetta to east of Champion Forest Drive.

Update: Work has begun along Spring Cypress Road to replace asphalt as part of an asphalt rehabilitation effort.
  • Cost: $6.5 million
  • Timeline: March 2026
  • Funding source: Harris County


3.) Asphalt rehabilitation package 2

Project: Asphalt rehabilitation for Hargrave Road from Hwy. 249 to Falba Road.
  • Cost: $1.4 million
  • Timeline: March 2026
  • Funding source: Harris County


4.) Stuebner Airline Bridge repairs

Project: Repair the bridge portion of Stuebner Airline Road over Cypress Creek near Cypresswood Drive.
  • Cost: $900,000
  • Timeline: December 2025
  • Funding source: Harris County