Upcoming projects
South Houston Avenue widening and reconstruction
Project: South Houston Avenue will be widened between Will Clayton Parkway and Atascocita Road, turning the existing two-lane asphalt roadway into a three-lane concrete roadway with curb and gutter. A new traffic signal system, drainage improvements—such as adding underground storm sewers—are also included in the project.
Update: Engineering work is 55% complete, according to Humble City Council July 24 meeting documents.
- Timeline: January 2026-January 2028
- Cost: $1.13 million (engineering/design services)
- Funding source: city of Humble
Project: Existing asphalt streets—including Meek and Manning roads—will be repaved under this project between North Houston Avenue and Townsen Boulevard. Construction will include installing new roadside drainage culverts, new water lines and fire hydrants along Meek Road.
Update: Engineering work is 60% complete, according to Humble meeting documents.
- Timeline: August 2025-January 2026
- Cost: $241,750 (engineering/design services)
- Funding source: city of Humble
Kingwood Drive improvements
Project: The Houston Public Works Department is working on upgrades to Kingwood Drive including repairing the curbs and the replacement of pavement markings at the intersection of Kingwood and Woodland Hills drives.
Update: The project was initially slated to run May 29-June 6, but the starting date shifted to late July as the contractor needed to complete a separate project first, said Erin Jones, HPW’s public information officer, via an Aug. 11 email.
- Timeline: late July-TBA
- Cost: $28,000
- Funding source: Houston District E Office