Read about some of the latest updates on transportation projects in the Katy-Fulshear area. This list is not comprehensive.
1. Harris Street reconstruction
Project: The project aims to improve Harris Street from FM 1093 to Fifth Street.
Update: At an April 21 meeting, Fulshear City Council approved a construction contract with iCON GC LLC for the second phase of the project.
- Timeline: May 7-late January 2027
- Cost: $2.3 million (Phase 2)
- Funding source: Fulshear Development Corps.