Project: This project will provide subdivision drainage improvements and pavement reconstruction for increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs in the Cypress Creek Estates subdivision.
Update: Funding for this project is approved and will focus on addressing drainage issues throughout the subdivision.
- Timeline: Estimated completion in fourth quarter 2026
- Cost: $10.1 million
- Funding source: federal grant managed by Harris County Engineering Department
6. Barwood subdivision improvementsProject: This project will provide the Barwood subdivision with drainage improvements and pavement reconstruction throughout the subdivision to increase drainage capacity, reduce flood risk and reduce long-term maintenance costs.
Update: This project has entered the construction phase, according to Harris County Precinct 3 officials.
- Timeline: estimated completion in second quarter 2026
- Cost: $1.1 million
- Funding sources: Community Development Block Grant, Harris County
7. Cypress North Houston Road