Here are four upcoming and ongoing transportation projects across the Cy-Fair area. This list is not comprehensive.

Upcoming projects

1.) Cypress Creek Estates Subdivision improvements

Project: Subdivision drainage improvements and pavement reconstruction for increased drainage capacity, reduced flood risk, and reduced long-term maintenance costs.
  • Cost: $10.1 million
  • Location: Cypress Creek Estates
  • Timeline: Fourth quarter 2026
  • Funding source: Harris County


2.) Cypress North Houston Road


Project: Widening roadway from two lanes to a four lane concrete boulevard with raised medians and underground storm sewer system. The project also includes new or upgraded traffic signals at Autumn Mills Road, Misty Moss Lane, and Perry Road.

Update: This project is in the design phase.
  • Cost: $16 million
  • Location: Cypress North Houston Road
  • Timeline: Design finalized by early 2026
  • Funding source: Harris County


Ongoing projects

3.) North Eldridge Parkway sidewalks


Project: Constructing sidewalks on both sides of North Eldridge Parkway from FM 529 to West Road.
  • Cost: $1.3 million
  • Location: North Eldridge Parkway
  • Timeline: End of 2025
  • Funding source: Harris County


4.) Grant Road widening
  • Project: Widen two-lane road to four lane boulevard from Telge Road to Shaw Road.
  • Cost: $1.3 million
  • Location: North Eldridge Parkway
  • Timeline: End of 2025
  • Funding source: Harris County