For the average West U household that does not receive a senior or disability exemption on its utility statements, the estimated impact will be an additional $2.36 per month.
Digging deeper
The bond proceeds, according to city officials, will be used for the following phases in these projects identified in the city’s 2025-34 Capital Improvement Plan:
- West Side drainage project: design phase for the city to explore future stormwater sewer improvements along the city’s west side
- Cast iron water line replacement: construction phase to replace cast iron water lines throughout the city
- Wakeforest water plant distribution line replacement: construction phase for the water distribution system in the northeast corner of the city to improve water pressure
- Milton water plant improvements: design phase to upgrade pump stations at the facility and replace two groundwater storage tanks
- Wakeforest elevated and ground storage tanks interior rehabilitation: design and construction phase to complete interior maintenance work on the storage tanks
How we got hereWest University's fiscal year 2025-2034 Capital Improvement Plan includes a roughly $502 million budget with 62%, or $312 million, of funds going toward drainage projects. CIP funds can be used to finance public improvements in the six following categories: drainage, facilities and technology, parks, streets, water, and wastewater.