Ongoing project
League City Parkway right turn lane
Project: An eastbound right-turn lane will be designed west of Butler Road to west of the I-45 southbound frontage road, and tie to the Texas Department of Transportation’s right-turn lane.
Update: Construction is ongoing.
- Timeline: anticipated completion by end of March
- Cost: $2.08 million
- Funding source: Galveston County bond funds
Extension of Hobbs Road to FM 517
Project: Approximately 1,880 feet of four-lane divided urban roadway will be constructed from the existing terminus south of the intersection of Patagonia Street and Hobbs Road to FM 517.
Update: The project plans are near completion, and are currently in right-of-way acquisition and TxDOT permitting phase, which will take the next several months.
- Timeline: anticipated bid date by late summer, pending ROW acquisition, with construction starting as early as late fall 2026 or early 2027
- Cost: $7.7 million
- Funding source: Galveston County and city funds
Project: To improve intersection capacity and safety, the project scope includes adding a long southbound right-turn lane and extending the existing northbound left-turn lane from 135 feet to 350 feet.
Update: Project plans are in review, with bidding beginning in the summer.
- Timeline: construction slated to start in late fall or early 2027
- Cost: $628,428
- Funding source: city cash funds