Upcoming projects
Clear Creek Avenue asphalt rehab
Project: will include reconstruction of the road from E. Walker Street to E. Galveston Street.
Update: Funding to come in 2026.
- Timeline: contract for construction awarded in October with work to start in January
- Cost: $365,013
- Funding source: funded through a community development block grant and city cash as needed
Project: includes construction of around 1.7 miles of four-lane road with two bridges and a boulevard to divide road
Update: Design for the project has been completed but work remains a couple years away
- Timeline: Texas Department of Transportation pushed bidding for project back to 2028, which could change based on the schedule to relocate utilities in the area.
- Cost: $66M for construction
- Funding source: TxDOT and local funding, with TxDOT estimated to cover $42 million
Project: include adding a traffic signal to Maple Leaf intersection of League City Parkway
Update: Design completed as of the end of October
- Timeline: Work could begin in May and will take about a year to complete
- Cost: $790,000 estimate
- Funding source: capital projects funds from city
Project: includes design and rebuild of traffic signal
Update: The design for the project is 100% complete and will go out to bid in early 2026
- Timeline: Work could begin May but will depend on signal equipment being delivered. The project could take around a year to complete.
- Cost: $573,000 estimated for project
- Funding source: city’s reinvestment funds
Hwy. 96 and Hwy. 3 intersection
Project: involved adding a left- and right-turn lane to help traffic mobility
Update: Work was completed in the spring.
- Timeline: began in spring 2023 and took two years due to delays with utility relocations
- Cost: $1.6M
- Funding source: city capital project funds