Work is slated to begin Nov. 1 on the first of two phases for a project connecting the MKT Trail to the White Oak Trail in the Heights.
Dubbed the MKT Spur Connector, the $1.1 million project will entail the creation of an 850-foot-long, 10-foot-wide reinforced concrete path connecting two existing trail pieces. From the existing MKT Trail, the new extension will travel east—over a White Oak Bayou tributary and under Studewood Street—before connecting the existing White Oak Trail.
Retaining walls with railings will be built along portions of the new trail. The project also involves the installation of 1,084 feet of storm sewer system, according to project officials.
The first phase involves dirt work, the construction of retaining walls and the construction of the drainage culvert over the White Oak Bayou tributary. That phase will run through next spring.