Throughout the year, Community Impact keeps track of future businesses and renovations that are occurring throughout the area. Here are 100 permits that were filed this year in the Heights, River Oaks and Montrose area. The following projects have been filed in the last year through the Texas Department of Licensing and Regulation.
1. Southwest Juice Bar: 8329 Beechnut St., Houston
Type of work: renovation/alteration
Timeline: Nov. 2, 2022-Jan. 16, 2023
Estimated cost: $50,000
2. KIPP Sharpstown Middle School: 8440 Westpark Drive, Houston
Type of work: renovation/alteration
Timeline: Feb. 1, 2023-June 1, 2023
Estimated cost: $800,000
3. Skin Laundry: 888 Westheimer Road, Ste. 127B, Houston
Type of work: renovation/alteration
Timeline: Jan. 6, 2023-March 31, 2023
Estimated cost: $150,000
4. Whole Foods Market: 701 Waugh Drive, Houston
Type of work: renovation/alteration
Timeline: June 1, 2023-Sept. 15, 2023
Estimated cost: $250,000
5. Harris County Civil Courthouse: 201 Caroline St., Houston
Type of work: renovation/alteration
Timeline: Jan. 2, 2023-June 2, 2023
Estimated cost: $500,000
6. Shipleys: 13646 Bissonnet St., Houston
Type of work: new construction
Timeline: Nov. 15, 2022-Jan. 31, 2023
Estimated cost: $240,000
7. Pizzana: 2029 W. Gray St., Houston
Type of work: renovation/alteration
Timeline: Nov. 14, 2022-April 10, 2023
Estimated cost: $375,000
8. 4 Ever Young: 550 Heights Blvd., Houston
Type of work: renovation/alteration
Timeline: Nov. 15, 2022-Jan. 31, 2023
Estimated cost: $100,000
9. Heyday: 2024 W. Gray St., Houston
Type of work: renovation/alteration
Timeline: March 8, 2023-May 10, 2023
Estimated cost: $300,000
10. Eagleclaw-Kinetik: 2700 Post Oak Blvd., Ste. 300, Houston
Type of work: renovation/alteration
Timeline: Nov. 22, 2022-April 30, 2023
Estimated cost: $150,000
11. Taco Bell: 2701 Yale St., Houston
Type of work: renovation/alteration
Timeline: Nov. 30, 2022-Feb. 28, 2023
Estimated cost: $100,000
12. Escape Game: 5015 Westheimer Road, Ste. A1178, Houston
Type of work: renovation/alteration
Timeline: Nov. 1-Dec. 15
Estimated cost: $190,500
13. MaKiin: 2651 Kipling St., Ste. 101, Houston
Type of work: renovation/alteration
Timeline: Jan. 9, 2023-April 30, 2023
Estimated cost: $1 million
14. O’Kane Theater: 1 Main St., Houston
Type of work: renovation/alteration
Timeline: May 1, 2023-Aug. 1, 2025
Estimated cost: $3.4 million
15. Consulate of Qatar: 1990 Post Oak Blvd., Ste. 900, Houston
Type of work: renovation/alteration
Timeline: Nov. 9, 2022-Jan. 11, 2023
Estimated cost: $210,000
16. Aburi Sushi: 3800 Southwest Freeway, Ste. 104, Houston
Type of work: renovation/alteration
Timeline: Nov. 28, 2022-March 1, 2023
Estimated cost: $400,000
17. Tesla: 10850 Louetta Road, Houston
Type of work: new construction
Timeline: Oct. 24, 2022-Oct. 28, 2024
Estimated cost: $150,000
18. SE Montrose: 3300 Montrose Blvd., Houston
Type of work: new construction
Timeline: Jan. 1, 2023-June 30, 2024
Estimated cost: $68 million
19. Heights Thrive Drip Spa: 2799 Katy Freeway, Ste. 210, Houston
Type of work: renovation/alteration
Timeline: Nov. 7, 2022-Feb. 1, 2023
Estimated cost: $250,000
20. Dogtopia: 2311 Washington Ave., Houston
Type of work: renovation/alteration
Timeline: Dec. 19, 2022-May 22, 2023
Estimated cost: $813,600
21. Brown Sims: 1990 Post Oak Blvd., Ste. 1350, Houston
Type of work: renovation/alteration
Timeline: Nov. 10, 2022-Feb. 10, 2023
Estimated cost: $362,000
22. Dutch Bros: 7128 Bellaire Blvd., Houston
Type of work: new construction
Timeline: Jan. 20, 2023-April 10, 2023
Estimated cost: $750,000
23. Houston Bank of Commerce: 1990 Post Oak Blvd., Houston
Type of work: renovation/alteration
Timeline: Nov. 17-Dec. 16
Estimated cost: $350,000
24. Toombs Imel: 777 Post Oak Blvd., Ste. 950, Houston
Type of work: renovation/alteration
Timeline: Oct. 31, 2022-Jan. 31, 2023
Estimated cost: $121,000
25. Leslie’s Pool: 2520 S. Voss Road, Houston
Type of work: renovation/alteration
Timeline: Nov. 15, 2022-Feb. 13, 2023
Estimated cost: $450,000
26. Golden Edge Barbershop: 2100 Travis St., Ste. 170, Houston
Type of work: new construction
Timeline: Nov. 1, 2022-March 1, 2023
Estimated cost: $67,800
27. Lady M: 5085 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Jan. 2, 2023-March 31, 2023
Estimated cost: $263,000
28. Houston Metro: 1900 Main St., Houston
Type of work: renovation/alteration
Timeline: Dec. 1, 2022-March 1, 2023
Estimated cost: $480,922
29. Ready Right Away: 3 Greenway Plaza, Houston
Type of work: renovation/alteration
Timeline: Oct. 25-Dec. 23
Estimated cost: $299,460
30. Natuzzi Italia: 1411 Uptown Park Blvd., Ste. 500, Houston
Type of work: renovation/alteration
Timeline: Oct. 31, 2022-Feb. 28, 2023
Estimated cost: $947,625
31. PNC Stadium: 2200 Texas Ave., Houston
Type of work: renovation/alteration
Timeline: Nov. 3, 2022-March 6, 2023
Estimated cost: $8 million
32. Urban Office: 540 Heights Blvd., Houston
Type of work: renovation/alteration
Timeline: Nov. 15, 2022-Feb. 15, 2023
Estimated cost: $985,000
33. Pattern Energy Houston: 888 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Nov. 17, 2022-May 5, 2023
Estimated cost: $4 million
34. The Venetian Nail Spa: 600 N. Shepherd Drive, Ste. 480, Houston
Type of work: renovation/alteration
Timeline: April 6-Sept. 23
Estimated cost: $50,000
35. Hi Skin: 600 N. Shepherd Drive, Ste. 420, Houston
Type of work: new construction
Timeline: Nov. 1, 2022-Feb. 1, 2025
Estimated cost: $150,000
36. Maria Tash: 5085 Westheimer Road, Ste. A2120, Houston
Type of work: renovation/alteration
Timeline: April 1, 2023-Aug. 31, 2023
Estimated cost: $1.2 million
37. Nori Sushi: 770 W. Sam Houston Parkway N., Ste 500, Houston
Type of work: renovation/alteration
Timeline: Nov. 14, 2022-May 31, 2023
Estimated cost: $400,000
38. The Studio Be: 888 Westheimer Road, Ste. 209, Houston
Type of work: renovation/alteration
Timeline: Oct. 31-Dec. 23
Estimated cost: $100,000
39. Removery: 9930 Katy Freeway, Houston
Type of work: renovation/alteration
Timeline: Oct. 21, 2022-Jan. 24, 2023
Estimated cost: $220,000
40. Wingstop: 11926 Wilcrest Drive, Houston
Type of work: renovation/alteration
Timeline: Oct. 1-Dec. 1
Estimated cost: $100,000
41. AIDS Foundation Houston: 2328 Fannin St., Houston
Type of work: renovation/alteration
Timeline: Nov. 30, 2022-April 1, 2023
Estimated cost: $1 million
42. Forum by Georgio’s: 5135 W. Alabama St., Ste. 7300, Houston
Type of work: renovation/alteration
Timeline: Oct. 17, 2022-Jan. 31, 2023
Estimated cost: $600,000
43. Stream Realty: 3040 Post Oak Blvd., Ste. 550, Houston
Type of work: renovation/alteration
Timeline: Oct. 10, 2022-Feb. 20, 2023
Estimated cost: $300,000
44. Kids Foot Locker: 5015 Westheimer Road, Ste. A1476, Houston
Type of work: renovation/alteration
Timeline: Jan. 9, 2023-Jan. 27, 2023
Estimated cost: $100,000
45. Heights Apartments: 333 W. 24th St., Houston
Type of work: new construction
Timeline: Dec. 1, 2022-March 31, 2025
Estimated cost: $31.2 million
46. Bally Houston: 5085 Westheimer Road, Ste. B2630, Houston
Type of work: renovation/alteration
Timeline: Nov. 1, 2022-Jan. 30, 2023
Estimated cost: $250,000
47. Best Buy: 5133 Richmond Ave., Houston
Type of work: renovation/alteration
Timeline: Jan. 9, 2023-May 1, 2023
Estimated cost: $1.7 million
48. Happy Lemon: 14248 Bellaire Blvd., Ste. 100, Houston
Type of work: new construction
Timeline: Oct. 15, 2022-April 30, 2023
Estimated cost: $140,000
49. Costco: 3836 Richmond Ave., Houston
Type of work: renovation/alteration
Timeline: Nov. 1-Dec. 1
Estimated cost: $90,000
50. Kura Sushi: 3510 S. Main St., Ste. A, Houston
Type of work: renovation/alteration
Timeline: Oct. 16-Nov. 14
Estimated cost: $150,000
51. SE7EN Restaurant: 3300 Kirby Drive, Ste. B, Houston
Type of work: renovation/alteration
Timeline: Aug. 31-Sept. 30
Estimated cost: $995,925
52. Bonobos: 4088 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Sept. 15-Nov. 15
Estimated cost: $250,000
53. Primrose School of Sawyer Heights: 1619 Ovid St., Houston
Type of work: new construction
Timeline: March 1, 2023-Dec. 31, 2023
Estimated cost: $3 million
54. Chopnblok: 401 Franklin St., Houston
Type of work: renovation/alteration
Timeline: Oct. 31-Nov. 28
Estimated cost: $65,000
55. Patrinely: 1980 Post Oak Blvd., Ste. 1900, Houston
Type of work: renovation/alteration
Timeline: Sept. 28-Dec. 28
Estimated cost: $850,000
56. SitusAMC: 5065 Westheimer Road, Ste. 700, Houston
Type of work: renovation/alteration
Timeline: Sept. 26, 2022-Jan. 30, 2023
Estimated cost: $300,000
57. QNC: 13838 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Sept. 26, 2022-April 21, 2023
Estimated cost: $1.3 million
58. Heatwave Gym: 1324 N. Shepherd Drive, Ste. 2509, Houston
Type of work: renovation/alteration
Timeline: Aug. 31-Sept. 30
Estimated cost: $100,000
59. Jamba Juice: 6405 West Road, Ste. 500, Houston
Type of work: renovation/alteration
Timeline: Aug. 8-Nov. 20
Estimated cost: $160,000
60. The Escape Game: 5015 Westheimer Road, Ste. A1178, Houston
Type of work: renovation/alteration
Timeline: Dec. 12, 2022-May 8, 2023
Estimated cost: $425,000
61. Reel Seafood & Bar: 2030 E. T.C. Jester Blvd., Houston
Type of work: renovation/alteration
Timeline: Nov. 1, 2022-March 1, 2023
Estimated cost: $110,000
62. Ready Right Away: 1990 Post Oak Blvd., Ste. 1400, Houston
Type of work: renovation/alteration
Timeline: Sept. 30-Dec. 31
Estimated cost: $619,000
63. River Oaks Aesthetic & Wellness Spa: 2111 West Loop S., Ste. 370, Houston
Type of work: new construction
Timeline: Jan. 2-Oct. 2, 2023
Estimated cost: $400,000
64. Gong Cha: 957 N. Shepherd Drive, Houston
Type of work: new construction
Timeline: Nov. 15, 2022-April 30, 2023
Estimated cost: $180,000
65. Tokyo Gas America: 5051 Westheimer Road, Ste. 1900, Houston
Type of work: renovation/alteration
Timeline: Oct. 1-Dec. 12
Estimated cost: $1.2 million
66. River Oaks Theater/Leo Restaurant: 2009 W. Gray St., Houston
Type of work: renovation/alteration
Timeline: Dec. 1, 2022-April 1, 2023
Estimated cost: $5 million
67. Starbucks: 11700 Westheimer Road, Ste. A, Houston
Type of work: renovation/alteration
Timeline: Feb. 27-May 4, 2023
Estimated cost: $695,900
68. Truist: 1400 Post Oak Blvd., Ste. 100, Houston
Type of work: renovation/alteration
Timeline: Oct. 17, 2022-March 15, 2023
Estimated cost: $982,000
69. PNC Bank: 2001 Kirby Drive, Houston
Type of work: renovation/alteration
Timeline: Aug. 29-Nov. 20
Estimated cost: $600,000
70. YSL: 5085 Westheimer Road, Ste. 3201, Houston
Type of work: renovation/alteration
Timeline: Oct. 24, 2022-Jan. 16, 2023
Estimated cost: $135,000
71. PNC Bank: 204 W. 19th St., Houston
Type of work: renovation/alteration
Timeline: Aug. 29-Nov. 30
Estimated cost: $500,000
72. Massage Envy: 1005 Waugh Drive, Houston
Type of work: renovation/alteration
Timeline: Aug. 20-Oct. 15
Estimated cost: $120,000
73. MADabolic: 8200 Washington Ave., Ste. 300, Houston
Type of work: renovation/alteration
Timeline: Sept. 19-Dec. 16
Estimated cost: $195,000
74. Kendall Heaton: 3050 Post Oak Blvd., Ste. 1000, Houston
Type of work: renovation/alteration
Timeline: Sept. 1-Dec. 19
Estimated cost: $200,000
75. Prada: 5085 Westheimer Road, Ste. B2580, Houston
Type of work: renovation/alteration
Timeline: Oct. 17-Dec. 8
Estimated cost: $452,800
76. Oxberry Midtown: 2627 Main St., Houston
Type of work: new construction
Timeline: Dec. 15, 2022-July 1, 2024
Estimated cost: $13 million
77. Jack’s Cafe: 1513 Cambridge St., Ste. N, Houston
Type of work: new construction
Timeline: Jan. 13, 2023-June 15, 2024
Estimated cost: $12.6 million
78. Montrose Blvd.: 3615 Montrose Blvd., Houston
Type of work: new construction
Timeline: Nov. 1, 2022-Feb. 1, 2025
Estimated cost: $130 million
79. Johnnie O’s: 2710-C Drexel, Houston
Type of work: renovation/alteration
Timeline: July 20-Sept. 15
Estimated cost: $135,000
80. Tall Grass: 9 Greenway Plaza, Level 8, Ste. 825, Houston
Type of work: renovation/alteration
Timeline: Sept. 1-Dec. 3
Estimated cost: $366,730
81. Ivory Bridal: 3015 Weslayan St., Ste. 105, Houston
Type of work: renovation/alteration
Timeline: Sept. 8-Dec. 30
Estimated cost: $1.3 million
82. WSS Shoes: 11560 Gulf Freeway, Houston
Type of work: renovation/alteration
Timeline: Sept. 1-Nov. 30
Estimated cost: $950,000
83. Ephemeral Tattoos: 1665 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Sept. 5-Dec. 5
Estimated cost: $150,000
84. Clean Juice: 3515 W. Dallas Ave., Ste. 800, Houston
Type of work: renovation/alteration
Timeline: Sept. 6-Nov. 21
Estimated cost: $300,000
85. Pineforest Jewelry: 6810 E. Sam Houston Parkway N., Houston
Type of work: new construction
Timeline: Aug. 15, 2022-March 15, 2023
Estimated cost: $2.5 million
86. Porta’vino Silo Bar: 7700 Washington Ave., Houston
Type of work: renovation/alteration
Timeline: Oct. 1, 2021-Feb. 3, 2023
Estimated cost: $500,000
87. Vivaldi Music: 1009 Yale St., Houston
Type of work: renovation/alteration
Timeline: Aug. 22-Nov. 18
Estimated cost: $300,000
88. Skyhouse: 2031 Westcreek Lane, Houston
Type of work: additions to existing building
Timeline: Sept. 1-Dec. 1
Estimated cost: $75,000
89. 7 Leaves Cafe: 11698 Bellaire Blvd., Ste. A, Houston
Type of work: new construction
Timeline: Sept. 15, 2022-March 30, 2023
Estimated cost: $190,000
90. PrimoHoagies: 4015 Washington Ave., Ste. E, Houston
Type of work: renovation/alteration
Timeline: Aug. 1-Nov. 1
Estimated cost: $245,000
91. Neiman Marcus: 2600 Post Oak Blvd., Houston
Type of work: renovation/alteration
Timeline: Jan. 2, 2023-Nov. 30, 2023
Estimated cost: $5 million
92. Pei Wei Asian Kitchen: 1249 N. Loop W., Houston
Type of work: renovation/alteration
Timeline: March 27, 2023-July 31, 2023
Estimated cost: $495,000
93. Burberry: 5015 Westheimer Road, Houston
Type of work: renovation/alteration
Timeline: Feb. 27, 2023-June 19, 2023
Estimated cost: $2.1 million
94. AP Sushi: 3540 West Dallas, Ste. 145, Houston
Type of work: new construction
Timeline: March 1, 2023-Sept. 30, 2023
Estimated cost: $300,000
95. M’s Beauty Lashes and Brows: 2795 Katy Freeway, Ste. 110, Houston
Type of work: new construction
Timeline: Aug. 15-Nov. 30
Estimated cost: $147,000
96. Lick Ice Cream: 3821 Bellaire Blvd., Houston
Type of work: renovation/alteration
Timeline: Feb. 1, 2023-May 31, 2023
Estimated cost: $300,000
97. Firehouse Subs: 2702 Yale St., Houston
Type of work: renovation/alteration
Timeline: Dec. 1, 2022-Feb. 18, 2023
Estimated cost: $400,000
98. River Oaks Jiu Jitsu: 4310 Westheimer Road, Ste. 240, Houston
Type of work: renovation/alteration
Timeline: Dec. 1, 2022-March 30, 2023
Estimated cost: $200,000
99. Sunright Tea Studio: 9938 Bellaire Blvd., Ste. L, Houston
Type of work: new construction
Timeline: Jan. 15, 2023-June 30, 2023
Estimated cost: $180,000
100. Crumbl Cookies: 11660 Westheimer Road, Ste. 119, Houston
Type of work: renovation/alteration
Timeline: Jan. 2, 2023-Feb. 28, 2023
Estimated cost: $320,000