The city of Southlake is moving ahead with landscaping plans on FM 1938/Davis Boulevard after a timetable adjustment by Texas Department of Transportation.
According to city documents, TxDOT is currently in design to construct raised medians on FM 1938 from FM 1709/Southlake Boulevard to the Southlake city limit through Keller city limits to Emerald Hills Way in North Richland Hills. The TxDOT project was scheduled for fiscal year 2025-26 and construction would begin in FY 2026-27, according to Southlake documents.
However, in March, Southlake officials learned the timetable had been pushed up and now approval of the TxDOT project is scheduled for November 2025 and construction could start in early 2026. No end date was listed by TxDOT.
The city awarded an engineering service agreement with Kimley-Horn in an amount not to exceed $125,000 for professional services for the development of construction documents and construction phases on June 18.