The City of Southlake is preparing for population growth and meeting water demands in the future, after the region experienced a record-breaking drought last summer.
The City Council recently adopted the Southlake 2030 Water System Master Plan to prioritize capital improvement projects, develop a water conservation plan and help guide funding recommendations for fiscal year 2013.
Southlake purchases its water supply from the City of Fort Worth. Southlake receives up to 10 million gallons of water per day from a 30- and 36-inch pipeline that runs from Fort Worth's Alta Vista's ground storage tank to Southlake's Pearson Road pumping station, according to the plan.
The city's current water demand is 26.9 million gallons per day on a peak day, Public Works Director Bob Price said. The projected 2030 water demand based on build-out of the city is 34.2 million gallons per day.