Several major road projects are making progress in the Grapevine, Colleyville and Southlake areas.
1. SH 26 Phase 2
On the SH 26 project in Colleyville, motorists can expect to see construction activity continue south of Centerpark Drive, including bridge work at Little Bear Creek bridge and concrete pavement placement on the east side of SH 26 near Brown Trail and Centerpark. Construction activity throughout the rest of the project will include continued preparation of the right of way area, asphalt prep work at various locations and concrete pavement placement at various cross streets. Main Street at SH 26 as well as Tinker Road at SH 26 is expected to be fully reconstructed and reopened at the end of September. The project consists of the widening of SH 26 from four lanes with a continuous left-turn lane to six lanes from John McCain Road to Brown.
Timeline: November 2016-2019 Cost: $38.2 million Funding source: Texas Department of Transportation
2. Pleasant Run Road reconstruction
Pleasant Run Road is open only to northbound traffic from L.D. Lockett Road to John McCain Road. Southbound traffic should detour from John McCain to SH 26 or John McCain to Westcoat Drive. Work through early September has consisted of utility relocation, placing an underground storm drain and more. Work will then shift to installing ribbon curb, sidewalks, subgrade preparation and paving. When complete, the road will be reconstructed from Shelton Drive to John McCain.
Timeline: July 2017-spring 2018 Cost: $4.9 million Funding source: city of Colleyville