FM 1938 Phase 2
[caption id="attachment_98758" align="alignright" width="109"]
FM 1938 Phase 2[/caption]
Traffic-control measures have been placed at the FM 1938 and FM 1709 intersection in Southlake to allow the contractor to begin work to widen this area. Installation of underground storm drainage is continuing. The reconstruction of Johnson Road has also started. The project is widening the roadway in each direction.
Timeline: April 2015-2017 Cost: $20.6 million Funding sources: Texas Department of Transportation; U.S. Department of Transportation; Federal Highway Administration; Tarrant County; the cities of Southlake, Trophy Club, Keller, Westlake; North Central Texas Council of Governments
FM 2499
[caption id="attachment_98759" align="alignright" width="112"]
FM 2499[/caption]
Crews completed concrete paving on the FM 2499 main lanes from SH 121 to Grapevine Mills Boulevard in Grapevine. Drainage, dirt and wall work continues on the new, lowered FM 2499 main lanes from Grapevine Mills to the north. Crews are also continuing to work on the southbound FM 2499 bridge over Denton Creek. Crews plan to set beams on this bridge by the end of the year.
Timeline: August 2013-January 2017 Cost: $93 million Funding sources: TxDOT, federal grant funds