Delays linked to the FM 2499 project near Grapevine Mills could continue for at least another two years as construction adds lanes and separates consumer traffic headed to the mall area from commuters headed to and from Flower Mound.
Kristen Stieg, spokeswoman for TxDOT contractor NorthGate Constructors, said the firm overseeing the project is hoping to have its work done by the end of 2016. That would bring the initial timeframe for total work in the area to more than three years, as construction on FM 2499 began in August 2013.
Steig said it is likely drivers will see traffic in its current state of congestion at the construction site through May 2015, when a new traffic switch could change overall flow.
The scope of the work
FM 2499 reconstruction was originally intended to be a part of the $1.6 billion DFW Connector project, but only $1.02 billion in funds were available when the larger-scale work was to begin on SH 114 and SH 121.