Colleyville’s proposed capital improvement program includes more than $35 million in drainage, streets and facilities projects.
Council members got an overview of the fiscal year 2026-27 capital improvement program during a work session July 21.
As part of the city’s budget adoption process, the list of projects in the capital improvement program will be finalized, according to a staff presentation.
The overview
Colleyville’s capital improvements program breaks down future projects over the course of five years and identifies a potential schedule and funding sources. For FY 2026-27, the total cost for all projects is $35.18 million, per the presentation.
“We have a variety of projects from various departments in the city,” Public Works and Parks and Recreation Director Lisa Escobedo said. “Some projects are multiyear or multifunded.”
According to city documents, projects slated for the FY 2026-27 program include:
- $8.15 million for the voting center/recreation center construction
- $5 million for the low water crossing on Bedford Road
- $2.5 million for the design of construction along Cheek-Sparger Road between Heritage Avenue and Bedford Road
- $1.5 million to add electricity to medians along SH 26
What else?
Escobedo said projects outlined in the draft plan are all cash-funded, meaning that there is not a need to issue debt to fund them.