A proposed utility project along East Hudgins Street in Grapevine is expected to begin next month.
Grapevine City Council approved up to $660,000 from the utility enterprise fund during the July 21 meeting. The contract, which is worth $594,264 with a contingency of $65,369, was awarded to Fort Worth-based contractor RUTS Construction.
Staff rounded the maximum expenditure up to $660,000, according to city documents.
The overview
The project will include new water and sewer mains along East Hudgins Street between South Dooley Street and South Main Street. Crews will install 1,500 feet of 8-inch water main and 1,500 feet of 8-inch sewer main along the roadway, per city documents.
Following the completion of the utility work, crews will reconstruct East Hudgins Street. The reconstruction is expected to last between four and six weeks.
During the project, no traffic will be able to access the project area, according to city documents.
The impact
By installing the new water and sewer mains, city staff anticipate several benefits, including:
- Taking an aging lift station out of service
- Providing capacity for a planned restroom expansion at the Grapevine Heritage Center and Historical Museum to accommodate attendance at Christmas Capital of Texas events
- Enhancing fire protection along the East Hudgins Street corridor
- Improving the water service capacity to the Grapevine Heritage Center and Historical Museum
Looking aheadConstruction is expected to begin in mid-August, and the contractor has 75 calendar days to complete the project, per city documents.
Public Works Director Bryan Beck said the construction should be completed by Thanksgiving.