Georgetown officials are looking to make improvements on multiple intersections and roadways throughout the city to improve functionality, manage capacity constraints and address an increase in motor crashes. The following roads and intersections will be undergoing improvements in the coming years.
UPCOMING PROJECTS
Hwy. 29
- Project: This project includes widening SE Inner Loop from Hwy. 29 to Sam Houston Avenue into a four-lane, divided roadway. SE Inner Loop from Sam Houston Avenue to FM 1460 will also be widened to a five-lane, undivided corridor. Additionally, a shared-use path for pedestrians and cyclists will be added. The intersections of SE Inner Loop at Southwestern Boulevard, Wey Hill Drive and Churchill Farms Drive are all proposed to have traffic lights with additional turn lanes, a city spokesperson said.
- Timeline: summer 2025-2026
- Cost: $32 million
- Funding source: city of Georgetown 2021 road bond
Shell Road
- Project: Work includes implementing additional turn lanes at the intersections of Williams Drive, Skyflower Drive, Madrid Drive, Sycamore Street and Bellaire Drive. A new signal and turn lanes will also be added at Village Commons Boulevard and Rosedale Boulevard. Additionally, 1.12 miles of Shell Road from Williams Drive to Sycamore Street will be widened to a four-lane road with a shared-use path on one side for pedestrians and cyclists.
- Timeline: spring 2024-2026
- Cost: $19 million
- Funding source: city of Georgetown 2021 road bond
Wildwood Drive and Williams Drive
- Project: A lane to turn right from southbound Wildwood Drive onto Williams Drive is planned for this intersection.
- Timeline: February 2024-summer 2024
- Cost: $150,000 (estimated)
- Funding source: city of Georgetown 2015 road bond
Williams Drive and Lakeway Drive/Bootys Crossing Road
- Project: This intersection has undergone several improvements, including the addition of dedicated turn lanes, which was completed earlier this year.
- Update: Additional improvements are now planned for this intersection. While the scope of work for the new improvements is still being determined, an additional lane will be implemented on Bootys Crossing Drive southwest of the intersection.
- Timeline: spring 2024-TBD
- Cost: $1.1 million
- Funding source: city of Georgetown 2015 road bond (design), TBD (construction)