Curious about which new businesses, restaurants and facilities are coming soon or underway in your backyard and beyond? Our commercial permit roundup helps identify what is being built in your community. The following commercial permits have been filed recently in Georgetown under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.
ESS/Retail Georgetown: 2801 W. University Ave., Georgetown
Type of work: new construction
Estimated cost: $9.7 million
Timeline: Sept. 15, 2022-July 15, 2023
Scope of work: three-story storage and retail building with on-grade baseball level, elevators, stairs and manager’s office; fully sprinklered
The Human Bean: 3117 Williams Drive, Georgetown
Type of work: new construction
Estimated cost: $225,000
Timeline: July 31-Dec. 31
Scope of work: new construction of shell and interior
Residence Inn Hotel: West University Avenue at I-35, Georgetown
Type of work: new construction
Estimated cost: $5 million
Timeline: July 15, 2022-July 15, 2023
Scope of work: new hotel project
Georgetown ISD's New Benold Middle School: 1401 N. Parmer Ranch Blvd., Georgetown
Type of work: new construction
Estimated cost: $63.9 million
Timeline: Sept. 7, 2022-Aug. 19, 2024
Scope of work: new Benold Middle School for Georgetown ISD
Anthony Medical & Chiropractic: Sedro Crossing, Georgetown
Type of work: renovation/alteration
Estimated cost: $409,000
Timeline: July 5-Sept. 6
Scope of work: tenant finish for a new chiropractic clinic
Loram Technologies: 3502 S. Austin Ave., Georgetown
Type of work: new construction
Estimated cost: $23 million
Timeline: Sept. 1, 2022-Dec. 18, 2023
Scope of work: new office and production facility
Titan Northpark35 Building VI: 1809 Titan Drive, Georgetown
Type of work: new construction
Estimated cost: $27.5 million
Timeline: Sept. 5, 2022-March 6, 2023
Scope of work: This project involves the design and construction of a new, one-story, 435,714-square-foot tilt-up concrete building located in Georgetown. It is anticipated that the building will contain primarily warehouse functions with accessory office spaces.
Waypoint West Building B: 6601 RM 2338, Georgetown
Type of work: new construction
Estimated cost: $400,000
Timeline: Sept. 1, 2022-Sept. 1, 2023
Scope of work: new construction of a shell retail one-story, 5,772-square-foot building
Liber & Company TI: 4045 Airport Blvd., Georgetown
Type of work: new construction
Estimated cost: $1.75 million
Timeline: Aug. 8-Dec. 12
Scope of work: tenant finish-out to shell building
Parkside on the River Phase 2, Section 5 & 6: Greenview Parkway, Georgetown
Type of work: new construction
Estimated cost: $4 million
Timeline: Nov. 1, 2022-Aug. 30, 2023
Scope of work: single-family residential, right-of-way, drainage, utilities and sidewalks