Here are 12 transportation projects that are upcoming and ongoing in Frisco, according to the city's capital improvement website.
This list is not comprehensive and more projects can be found on the city's website.
Upcoming
Legacy & Stonebrook widening
Project: Legacy Drive will be widened from Lebanon Road to Stonebrook Parkway. Stonebrook will be widened from Legacy to 4th Army Drive. The roadway will be widened and reconstructed.
Update: The project is in the design phase and expected to start construction later this year.
Hillcrest Road construction
Project: Hillcrest Road is expected to be constructed from Eldorado Parkway to Main Street.
Update: The project is in the planning phase. The project is also expected to include a water line update.
Legacy Drive upgrades
Project: Legacy Drive will be updated from Main Street to Panther Creek Parkway though project details are not yet available.
Update: The project is in the design phase with construction bidding expected to start in mid 2028.
Frisco Street construction
Project: Frisco Street will be constructed into a four-lane roadway from Eldorado Parkway to Panther Creek Parkway.
Update: The project is in the design phase and expected to start later this year.
John Hickman construction
Project: John Hickman Parkway will be constructed from Dallas North Tollway to Parkwood Boulevard. The project borders The Mix project at the corner of Lebanon Road and Dallas North Tollway.
Update: The project is in the design phase and project details are not yet available.
Warren Parkway improvements
Project: Warren Parkway will be updated from Legacy Drive to Gaylord Parkway.
Update: The project is in the design phase and project details are not yet available.
Frisco Street roundabout additions
Project: Frisco Street will see four new roundabouts added at Technology Drive, Sports Village Road, All Stars Avenue and Research Road.
Update: The project is in the design phase with construction bidding set to begin in early 2027.
Ongoing
Lebanon Road widening
Project: Lebanon Road is being widened from a four-lane divided roadway to a six-lane divided roadway. The project spans FM 423 to Todd Drive.
Update: The project is under construction and is expected to be completed late next year.
Ohio Drive roundabout addition
Project: The intersection at Ohio Drive at Gaylord Parkway will be converted into a roundabout.
Update: The project is under construction and expected to be completed early next year.
King Road construction
Project: King Road will be under construction to construct a third and fourth lane from Rose Lane to Witt Road.
Update: The project is under construction and expected to wrap next year.
PGA Parkway updates
Project: PGA Parkway will be updated to be a six-lane divided roadway from Preston Road to Coit Road.
Update: The project is under construction and expected to be completed this year.
Teel Parkway construction
Project: Teel Parkway will be widened from a two-lane roadway to a four-lane divided roadway from Stafford Middle School to Olive Branch Road.
Update: The project is under construction and is expected to be completed in early 2027.