Local construction company Mario Sinacola & Sons Excavating, Inc. is expected to begin construction of a new road between FM 423 and Teel Parkway in February after Frisco City Council authorized a construction contract Jan. 3.
Fields Parkway will be constructed as a four-lane thoroughfare that extends the road project already under construction between Dallas Parkway and Teel Parkway, according to a staff report. The road’s west portion will follow the existing Little Ranch Road alignment while the east portion will feature new construction, according to a project map.
Once complete, the new road will serve as a new east-west connection between FM 423 and the Dallas North Tollway.
The $13.3 million project includes paving improvements, drainage improvements, a multi-lane roundabout at the intersection of Fields Parkway and Teel Parkway and a traffic signal at Teel Parkway and PGA Trail, according to the staff report.