Here are 12 transportation projects that are upcoming or ongoing in Frisco, according to the city's capital improvement website. This list is not comprehensive.
Upcoming projects
1. Legacy Drive updates
Project: Legacy Drive will be updated from Main Street to Panther Creek Parkway.
Updates: The project is in the planning phase, and details regarding the project are not yet available.
- Timeline: mid-2027-mid-2029
- Cost: $23 million
- Funding sources: city of Frisco, external funding
2. Panther Creek Parkway widening
Project: Panther Creek Parkway will be widened from a four-lane roadway to a six-lane roadway from Preston Road to Coit Road.
Update: The project is in the planning phase, and construction is expected to start next year.
- Timeline: mid-2027-late 2029
- Cost: TBD
- Funding source: TBD
3. Hillcrest Road construction
Project: The project will construct a four-lane divided roadway from Eldorado Parkway to Main Street.
Update: The project is in the planning phase.
- Timeline: early 2028-mid-2029
- Cost: TBD
- Funding source: TBD
4. Warren Parkway upgrades
Project: Warren Parkway will be updated from Legacy Drive to Internet Boulevard.
Update: The project is in the design phase, and project details are not yet available.
- Timeline: early 2027-mid-2028
- Cost: $4.2 million
- Funding source: city of Frisco
5. Rolater Road improvements
Project: The project will space Rolater Road from Preston Road to Kings Ridge Road.
Update: The project is in the planning phase, and project details are not yet available.
- Timeline: TBD
- Cost: TBD
- Funding source: TBD
6. Ohio Drive roundabout addition
Project: A roundabout will be added to the Ohio Drive and Wade Boulevard intersection.
Update: The project is in the planning phase and is expected to start construction next year.
- Timeline: early 2027-early 2028
- Cost: $4 million
- Funding source: city of Frisco
Ongoing projects
7. Mahard Parkway construction
Project: Mahard Parkway is being constructed to a six-lane roadway from PGA Parkway to US 380. The road will border the Firefly Park development.
Update: The project is under construction and expected to be completed later this year.
- Timeline: late 2024-late 2026
- Cost: $11.03 million
- Funding source: city of Frisco
8. Dallas Parkway widening
Project: Dallas Parkway is being updated to include additional lanes on northbound and southbound frontage roads from Panther Creek Parkway to PGA Parkway.
Update: The project is under construction and is expected to wrap this year.
- Timeline: early 2025-mid-2026
- Cost: $18.39 million
- Funding source: city of Frisco
9. Teel Parkway widening
Project: Teel Parkway is being widened from a two-lane divided roadway to a four-lane divided roadway from Stafford Middle School to Olive Branch Road.
Update: The project is under construction and is expected to be completed by early next year.
- Timeline: mid-2025-early 2027
- Cost: $9.36 million
- Funding sources: city of Frisco, external funding
10. PGA Parkway construction
Project: The project will construct a six-lane divided roadway along PGA Parkway from Preston Road to Coit Road.
Update: The project is under construction and is expected to be completed later this year.
- Timeline: late 2024-mid-2026
- Cost: $31.1 million
- Funding sources: city of Frisco, external funding
11. Lebanon Road widening
Project: Lebanon Road is being widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive.
Update: The project is under construction.
- Timeline: mid-2025-late 2027
- Cost: $23 million
- Funding sources: city of Frisco, external funding
12. Fields Parkway traffic light addition
Project: A traffic light is being installed at the Fields Parkway and Dallas Parkway intersection.
Update: The project is in its last months of construction.
- Timeline: mid-2025-mid-2026
- Cost: $350,000
- Funding source: city of Frisco