Update: The project is in the early planning phase. Project details are not yet available on the city’s capital improvement website, but it's expected to start construction in early 2027.
- Timeline: early 2027-mid-2028
- Cost: $19 million
- Funding source: city of Frisco, external funding
2. Legacy Drive widening Project: Legacy Drive is set to be widened and reconstructed from Lebanon Road to Stonebrook Parkway and Stonebrook Parkway to 4th Army Drive.
Update: The project is in the design phase and is expected to start construction later this year.
- Timeline: mid-2026-late 2027
- Cost: $18 million
- Funding source: city of Frisco
3. Panther Creek Parkway widening Project: Panther Creek Parkway is set to be widened from a four-lane roadway to a six-lane roadway from Preston Road to Coit Road.