Check out 10 transportation projects happening in Frisco, according to the city’s capital improvement site:
Upcoming
1. Oak Street reinvestment
Project: Oak Street will be updated from Second Street to North County Road. Project details are not yet available online.
Update: The project is still in the planning stage.
- Timeline: TBD
- Cost: $3 million
- Funding source: city of Frisco, external funding
2. Ohio Drive and Wade Boulevard roundabout additions
Project: The roundabout at Ohio Drive and Wade Boulevard will be renovated into a multi-lane roundabout.
Update: The project is still in the planning stage.
- Timeline: TBD
- Cost: $4 million
- Funding sources: city of Frisco, external funding
3. Hillcrest Road construction
Project: Hillcrest Road will be updated from SH121 to Main Street.
Update: The project is in the planning phase, with its design phase set to end in 2027.
- Timeline: late 2027 - late 2028
- Cost: $12 million
- Funding sources: city of Frisco, external funding
4. Legacy Drive widening
Project: Legacy Drive will be widened from Lebanon Road to Stonebrook Parkway. Stonebrook Parkway will also be widened from Legacy Drive to 4th Army Drive as part of the project. The roadways will also be reconstructed along with the widening.
Update: The project is currently in the design phase. Construction is set to start later this year.
- Timeline: mid 2026-mid 2028
- Cost: $20 million
- Funding source: city of Frisco
Ongoing
5. Preston Road and Corporate Drive traffic signal addition
Project: A new traffic signal is being added to the intersection of Corporate Drive and Preston Road.
Update: The project is in the design phase.
- Timeline: Late 2025 - late 2026
- Cost: $300,000
- Funding sources: city of Frisco, external funding
6. Lebanon Road widening
Project: Lebanon Road is being widened from a four-lane roadway to a six-lane roadway. The project spans from FM 423 to Todd Drive, which is just west of Legacy Drive.
Update: The project is under construction and expected to be completed next year.
- Timeline: mid 2025-late 2027
- Cost: $23 million
- Funding Sources: city of Frisco, Denton County
7. PGA Parkway construction
Project: PGA Parkway will be expanded into a six-lane roadway from Coit Road to Preston Road.
Update: The project is under construction and is expected to be completed later this year.
- Timeline: late 2024-fall 2026
- Cost: $31.1 million
- Funding Sources: city of Frisco, external funding
8. Mahard Parkway construction
Project: Mahard Parkway is being constructed as part of the Firefly Park development. The six-lane road will span PGA Parkway to US 380.
Update: The project is under construction and is expected to be completed by the fourth quarter of 2026.
- Timeline: late 2024-late 2026
- Cost: $11.03 million
- Funding Source: city of Frisco
9. Teel Parkway widening
Project: Teel Parkway is being widened from a two-lane roadway to a four-lane roadway. The project spans from Olive Branch Road to Stafford Middle School.
Update: The project is under construction and will be completed early next year.
- Timeline: mid 2025-early 2027
- Cost: $9.36 million
- Funding Sources: city of Frisco, external funding
10. King Road construction
Project: King Road is being updated to include two new lanes along the roadway from Rose Lane to Witt Road, bringing King Road to four lanes total.
Update: The project is under construction and is expected to be completed next year.
- Timeline: late 2025-mid 2027
- Cost: $12.5 million
- Funding sources: city of Frisco, external funding