Stonebrook Parkway
Construction is now complete on the east portion of Stonebrook Parkway from Preston Road to the Dallas North Tollway. The road was widened to six lanes.
The fifth and sixth lanes on the west portion of Stonebrook Parkway from DNT to Longhorn Trail are still under construction. Construction for that portion of the road is about 85 percent complete. The project includes also constructing a new six-lane roadway to connect Fighting Eagles Lane to Longhorn Trail.
Timeline: Construction is complete (east side), October 2015 (west side) Cost: $14.38 million (east portion), $17.75 million (west portion) Funding sources: city of Frisco, Texas Department of Transportation, North Central Texas Council of Governments.
Teel Parkway
Construction began this spring to extend Teel Parkway from Stafford Middle School to Rockhill Parkway. The new roadway will be a two-lane asphalt road.