The Public Utility Commission of Texas approved the final order for the planned power lines project in West Frisco during its June 9 meeting, about a year after electric provider Brazos Electric filed its application to build the lines with the PUCT.
Construction for the hybrid overhead/underground power lines route—which spans from west of FM 423 to east of Legacy Drive on Main Street—is expected to begin by next fall.
The process to finalize this power lines project resulted in multiple public meetings in Austin, the rallying of residents to create the Bury the Lines advocacy group and the city of Frisco agreeing to contribute more than $12 million to have the lines buried.