Brazos Electric on Jan. 15 officially filed a certificate of convenience and necessity with the Public Utility Commission of Texas for additional power lines in west Frisco.
As both Brazos Electric and CoServ Electric officials have said would happen in recent months, the CCN includes proposals for both underground and overhead routes along either Stonebrook Parkway or Main Street.
Brazos Electric estimates the cost of underground lines would be $42.6 million, while the estimated cost of overhead lines is $13.7 million.
"The proposed project will provide for increase reliability and better continuity of service for Brazos Electric's member cooperatives and its member customers," Brazos said in filing notifications.