The FISD board approved roofing projects for Maus Middle School, Mooneyham Elementary School, Heritage High School, Ashley Elementary School, Ogle Elementary School, Scoggins Middle School, Comstock Elementary School and Elliot Elementary School.
The repairs and replacements will cost a little over $10.2 million with a contingency allowance, according to district documents. This will be funded from the hail-damaged roof replacement and repair proceeds received from FISD’s insurer and local capital funds, per district documents.
Pioneer Heritage and Wester middle schools will receive roofing maintenance repairs for nearly $1.5 million with a contingency allowance. Funding will come from the 2018 bond program, per district documents.
Lighting upgrades