Stay up to date on road projects happening in Flower Mound and Argyle, including traffic signal reconstruction at Cross Timbers Road and Luther Lane, and turn lane additions on Long Prairie Road.
Upcoming projects
1. Flower Mound traffic signal improvements
Project: Town officials plan to reconstruct the traffic signals at the Cross Timbers Road and Luther Lane and build new signals at the Flower Mound Road and Quail Run Road intersection as part of an annual project. Pedestrian signals and Americans with Disabilities Act-accessible ramps will be added to the intersection of Old Settlers Road and McKamy Creek Road.
Update: Flower Mound Town Council approved a professional services contract worth $103,000 with Kimley-Horn and Associates to design the improvements during the March 2 meeting.
- Timeline: TBD
- Cost: $1.25 million
- Funding source: town of Flower Mound
2. FM 407 widening projectProject: The road will be widened from two lanes to six lanes between Bill Cook Road and FM 1830. A shared-use path and sidewalk will also be included to accommodate bicyclists and pedestrians.
Update: A public hearing on the project is scheduled for April 9.
- Timeline: TBD
- Cost: $171 million
- Funding source: Texas Department of Transportation
3. I-35W frontage roads expansionProject:
The work includes constructing frontage roads on I-35W from 0.7 miles south of FM 407 to FM 2449, according to TxDOT documents.
Update: TxDOT is working to acquire right of way for the project, move utilities and finalize design plans. The project is planned to go out to bid for construction in December 2027.
- Timeline: TBD
- Cost: $260.7 million
- Funding source: TxDOT
Ongoing projects4. Long Prairie Road turn lane addition
Project:
Crews are currently adding a right-turn lane and cutout left-turn lane to enter a new commercial development along Long Prairie Road.
Update: The right lane for southbound traffic is currently closed while crews build the right-turn lane into the development.
- Timeline: TBD
- Cost: TBD
- Funding source: TBD
5. Scenic DriveProject: Workers are making pavement repairs along Scenic Drive between Cross Timbers Road and the intersection with Walsingham Drive and at the Walsingham intersection. Pavement repairs are done to replace deteriorated concrete sections of the road, Flower Mound officials said.
Update: During the project, drivers should expect closures in the area with two-way traffic implemented on Walsingham Drive. If needed, detours will be arranged using surrounding roads.
- Timeline: March 2-April 10
- Cost: TBD
- Funding source: town of Flower Mound
Completed projects6. Sunset Trail
Project:
Construction crews worked to replace a 48-inch water pipe along Sunset Trail between Rocky Point and Ridgecrest Drive.
Update: Crews have completed work on the project, along with nearby drainage improvements. The road has also reopened after a closure was required during the project.
- Timeline: Jan. 27-Feb. 27
- Cost: $50,000
- Funding source: town of Flower Mound